| S/N | Project Title | Location | Scope of Work | Status |
|---|---|---|---|---|
| 1 | Installation of Electric Vehicle Charging Stations across Lagos | Lagos |
- Determination of requirements and design of the power supply infrastructure for all locations. - Procurement and installation of substation equipment. - Installation of EV charging stations. - Testing and Commissioning. |
Design phase completed |
| 2 | Installation of 2x30kWp Solar PV Power Solution for Lagos restaurant | Lagos |
- Front end engineering design - Shipping and procurement of major equipment and long-lead items - Construction and installation |
Design completed |
| 3 | 1.5MVA 33/0.4kV Transformer Substation for food processing company, Ikorodu, Lagos | Lagos |
- Engineering design. - Supply and installation of 1.5MVA 33/0.4kV Transformer, switchgear and cables. - Supply and installation of 33kV 30/5A CTVT HVMD Meter, 2500A ACB Panel. - Supply and installation of 2500A LV Distribution Panel with Auto-Transfer Scheme and Generator Synchronization Panel |
Completed |
| 4 | 750kVA 11/0.4kV Transformer Substation for Polymer and Plastics company, Ikeja, Lagos./td> | Lagos |
- Engineering design. - Supply and installation of 750kVA 11/0.4kV Transformer and switchgears. - Supply and installation of HVMD Meter |
Completed |
| 5 | 200kVA 11/0.4kV Substation for food processing company, Ogun State, Nigeria. | Ogun State |
- Engineering design. - Construction of 0.4km of 11kV overhead line. - Supply and installation of 200kVA 11/0.4kV Transformer and substation switchgear. - Supply and installation of 400V Distribution Panel. - Supply and installation of 400/5A LV CT Meter |
Completed |
| 6 | 300kVA 33/0.4kV Substation for manufacturing company, Ikorodu, Lagos. | Lagos |
- Engineering Design. - Supply and installation of: - 300kVA Transformer and substation switchgear. - 1km of 33kV overhead line. - 33kV 205A CTVT MD Meter. - 400V Automatic Change-Over and Distribution Panel. |
Completed |